Exterior of Facility Showing Utility Electrical Service Entrance with 500 KVA Transformer
2000 amp Utility Service Entrance Distribution with three (3) Facility Main Service Disconnect Breakers. One (1) x 800 amp, Two (2) x 600 amp. "Six Subdivision Rule" Applies In This Application
Site Preparation - Core Drilling Facility Exterior Wall
2000 Amp Generator Quick Connect Switchboard" Set In Place and Ready For Wiring
Electrical Conduit Installation
Wire Installation to "Generator Quick Connect Switchboard"
Wire Installation From "Generator Quick Connect Switchboard" Into Three (3) Facility Service Disconnect Breakers
Installation of Triple (3) Trapped Key Interlock on 2000 Amp "Generator Quick Connect Switchboard" Note: All Trapped Keys from the Three (3) Facility Service Main Disconnect Breakers Must Be Inserted Before This Trapped Key Interlock Can Be Activated.
Installation of Trapped Key Interlock on Facility Main Service Number One - 600 Amp
Installation of Trapped Key Interlock on Facility Main Service Number Two - 600 Amp
Installation of Trapped Key Interlock on Facility Main Service Number Three - 800 Amp
2000 Amp "Generator Quick Connect Switchboard"Total Project Completion Time: 3 DaysUtility Power Cut Off Time: 5 Hours